This post presents the actual construction process of wind power project from design survey to completion of construction.

Investigation, Design

Site survey, implementation, design & detailed planning.

Piling Work

1/Delivery pile from factory to fabrication yard for splicing/combination and marking

2/Delivery pile from fabrication yard to site for piling barge

3/Driving pile by flying hammer with guide frame for WTG foundation and Link Bridge

4/Driving pile by piling barge for WTG foundation and Link Bridge

Concrete Work

1/Installation clamp and support system

2/Cut-off pile head; Installation rebar and pouring concrete for pile plug

3/Installation rebar, formwork, grouding system, anchor cage and pouring concrete for lift 1

4/Installation rebar, formwork, conduit, cooling system, and pouring concrete for lift 2

5/Installation rebar, formwork, and pouring concrete for lift 3

6/Girder installation for LB

7/Handrail installation and final completion